  1. Electronics Assembly  You will need:
    • Electronics Assembly You will need:

    • The SatNOGS v2 Mechanical Ground Station Assembly.

    • TP-Link WR703N

    • SatNOGS PCB

    • SatNOGS PSU PCB

    • A 4 port USB hub

    • 2 USB micro cables

    • One double wire for 12V to SatNOGS PCB

  2. Using double sided foam tape, place the TP Link on the side as shown. Place SatNOGS PCB as shown (with foam tape) Place SatNOGS PSU PCB as shown (with foam tape)
    • Using double sided foam tape, place the TP Link on the side as shown.

    • Place SatNOGS PCB as shown (with foam tape)

    • Place SatNOGS PSU PCB as shown (with foam tape)

    • Stick with foam tape and connect the USB hub as shown.